A tipper that waits for a slow loading team, or drives across the metro to an open landfill, costs more than the load is worth. This calculator works out how many loads the volume takes in a 6 cube tipper, a 10 cube tipper or a side tipper, how many trips that is, how long loading takes by hand or by machine, the driving and tipping time for the distance you give, and the hours and days in total. The tipper truck hire page covers what to ask.
What goes into the hours
The loads come from the loose cubes and tonnes, whichever fills the truck first. Each trip then adds three things: loading, driving to the tip and back at an average town speed, and time at the landfill for the queue, the weighbridge and tipping.
Hand loading uses about half a cube an hour for each worker with a wheelbarrow and spade, derived from published labour based work norms. Machine loading uses our default rate for each machine, worked out from its bucket size with a textbook production method. Speed and tipping time are our defaults too; change any of them.
Reading the result
- Loads: how many times the truck fills.
- Trips: loads per truck if you run more than one.
- Loading hours: often the largest part of the day, and the part you control.
- Total hours and days: what a truck hired by the hour or the day will charge for.
If loading by hand takes days, the line for a TLB or a bobcat shows what plant would change; the TLB hire page explains minimums and travel.
Where the plan slips on the day
- The tipper arrives before the TLB, or the other way round, and one stands paid.
- The landfill queue on a Friday afternoon doubles the tipping time.
- The heap is behind the house and every barrow goes through a gate and up a ramp.
- Rain turns the site to mud and loaded trucks cannot get out.
- The truck runs overweight on wet clay and has to tip some off.
- The nearest site does not take that material, and the drive is twice as far.
Booking trucks from the numbers
Put the volume, the truck size, the loading method and the distance on the request below. Tipper owners quote by the load, the hour or the day, so say which you want compared. Ask whether loading is included, how many workers come with a hand loaded truck, what standing time costs, and for the weighbridge slip from each trip. For bulk earthworks with long hauls, a side tipper may cost less per tonne, if it has room to turn and tip.
Sources
- International labour body, productivity norms for labour based work: recommended task rates: loading 8.5 loose m³ a worker day; wheelbarrow haul 8.5 m³ a day up to 20 m, 7.0 to 40 m, 6.5 to 60 m; hand loading above about a metre is very hard
- Backhoe loader dealer, TLB shovel capacities: front shovel capacity 1.0 m³ on the standard TLB; 0.7 m³ on the compact and 1.2 m³ on the larger version
- Compact equipment maker, standard skid steer bucket: ISO heaped capacity 0.30 m³ (1,422 mm wide), 0.34 (1,575 mm), 0.38 (1,727 mm), 0.41 m³ (1,880 mm)
- Excavator maker, 2.5 ton mini excavator datasheet: operating weight 2,550 kg; bucket capacity 0.033 to 0.09 m³
- Excavator maker, 20 ton class excavator specifications: operating weight 22,700 kg with a reach boom; buckets 1.0 m³ and 1.19 m³ heavy duty
- University course notes, excavator production estimating: production = cycles an hour x swing factor x heaped bucket x fill factor x job efficiency; example: a 0.57 m³ excavator at 250 cycles an hour, fill 0.95, 50 working minutes an hour gives 113 loose m³ an hour
- Kempton Park rubble removal operator, business listing: 6 cube (8 ton) tippers for rubble removal; also 10 cube tippers
- Truck maker, 6 m³ tipper chassis leaflet: 6 m³ tipper: GVM 16,200 kg, tare 5,265 kg, permissible body and payload 10,935 kg
- Truck maker, 10 m³ tipper leaflet: 10 m³ tipper box; GVM 25,500 kg; tare total 8,500 kg
- Trailer maker, interlink side tipper specifications: interlink side tippers: 25 m³ with 36,550 kg payload, 40 m³ with 35,340 kg, 45 m³ with 34,780 kg; GCM 56,000 kg
- South African plant hire firm, 10 cube tipper and plant: 10 cube (10 m³) tipper truck hired by the 9 hour day; the firm's TLB and 20 ton excavator are also on a 9 hour standard shift, short term daily hire
- Gauteng plant hire site, TLB hire terms: the minimum hire period is one day; daily to long term hire
Frequently asked questions
How long does it take to load a 6 cube truck by hand?
Why does the distance to the landfill matter so much?
Is a 10 cube tipper always cheaper than a 6 cube?
Who will quote for the trucks and loading?
More calculators and tools
- Rubble volume calculatorCubes as it lies, cubes once loaded, and the tonnes it weighs
- Skip size calculatorEvery bag, skip and truck for your load, by volume and by weight
- Demolition waste calculatorThe rubble a wall, a garage or a house leaves when it comes down
- Removal cost calculatorBags, skips, a trailer and tippers priced for the same job
- Garden refuse calculatorBags, branches, palms and lawn cuttings in cubes and loads
- Landfill fee calculatorWhat tipping a load costs at the weighbridge, and the sums